The Contractor shall remove, raise, and reinstall the existing Fire Suppression pipes on the= roofs of Facility C- Building 701, 702, and 703 and Facility D -Building 706, 707, 708, and 709= housing units. The Contractor shall supply all the material needed including pipe markers, valve= tags, equipment nameplates, and all other items deemed necessary, and in accordance with the= Plans and Specifications. The Contractor shall: Supply a complete set of shop drawings showing the work that the Contractor is to= perform Connect new Fire Sprinkler pipe to nearest possible point of connection. Provide markup= of drawings showing connection point to existing riser for Architecture & Engineering= (A&E) review and approval per Request For Information (RFI) number 011 Conform to applicable Codes and Regulations, and as identified in the project Plans and= Specifications Be present for and perform all Acceptance and Testing of equipment and devices with= the Office of the State Fire Marshal (OSFM) for each phase Work with the IWL Site Supervisor or designee and cooperate with CDCR staff and all= trades during all phases of work to resolve design or field conflicts