Construction activities will be carried out in the following sequence: 1. Clearing and grubbing: maximum area of disturbance at any one time 5 acres. 2. Site preparation, grading and installation of gravel road and utilities (electricity and communications, etc.). 3. Installation of photovoltaic structures, including the equipment pad and point of interconnect. 4. Landscaping with drought resistant landscape plants at the south end of the property as a buffer between the solar facility and the nearby residence. This landscape buffer will be irrigated by an existing District well on the property, as appropriate. 5. An existing disturbed area adjacent to the northwest edge of the solar facility will be used as the project staging area.