General Description – The work to be performed under this contract includes the removal and replacement
of existing concrete pavement, pattern concrete, sidewalk, curb and gutter, mountable curb, gutter and walk,
crosspan (10” thick), curb ramp (6” thick), 4” sidewalk, and 6” sidewalk. The Contractor shall supply all labor,
equipment, and materials necessary to complete the work in accordance with these specifications. The
contract shall be awarded based on bids received and the contract documents. Contractor will be required
to coordinate construction activities with adjacent businesses, trash removal companies, school district, HOA,
Metro Districts, and other Town maintenance projects if applicable. The contractor shall commence work no
later than three (3) calendar days from, and including, the date of the Notice to Proceed, and be construction
complete (punchlist items, cleanup, and demobilize) within forty (45) working days from the date on the Notice
to Proceed. If “Construction Completion” is not issued within the allotted contract time for the original scope
of work, “Liquidated Damages” shall be assessed. When contract work is complete, the contractor shall
commence work on punchlist items, cleanup, and demobilizing regardless of contract time remaining. Work
shall take place between April 10, 2023 and June 12, 2023. A schedule of sequencing of all work shall be
submitted at or before the project pre-construction meeting, and approved by the Town prior to issuance of
Notice to Proceed.