Specifications include, but are not limited to: 1. Coordination of schedule between the unit, contractor, and project manager. 2. Coordination of work areas for phases I and II. 3. Most all equipment can and will be disconnected and relocated by the unit staff including washer, dryer, and ice machine. 4. Contractor shall be responsible for working around the breathing air machine (unless it can be cautiously lifted in some fashion), eye wash / shower and double basin sink. 5. If the alternate is accepted, it will be done with one of the two phases of work. 6. Unit to move all equipment out of phase I work area into phase II work area. 7. Contractor to grind, polish, fill voids and seal phase I work area. 8. Unit to move all equipment out of phase II and back into phase I work area. 9. Contractor to grind, polish fill voids and seal phase II work area. 10. Contractor to clean up each phase prior to turning it back over to the unit. 11. Unit to return all equipment back into the appropriate spaces as needed.