Specifications include, but are not limited to: all materials, equipment, transportation, and labor necessary to complete the improvement generally described as follows: traffic signal removal and replacement, driveway removal and replacement, PCC patching, ADA sidewalk ramp construction, and surface restoration at the intersection of W. 2nd Avenue and S. Buxton Street. The project includes 4 traffic signal mast arm poles, 2 pedestrian push button poles, approximately 185 SY of roadway, driveway, and sidewalk pavement removal, 61 SY of PCC sidewalk, 76 SY of full depth patching, 90 SY of modified subbase, removal, grooving, and application of pavement markings, temporary traffic control, erosion and sediment control, sodding, and associated general construction, including cleanup. The project also includes alternates for fiber optic and wireless communication interconnection systems.