Quote Package #01 – Masonry Repairs a. Includes specification sections: i. 04 0100 – Maintenance of Masonry ii. 04 2000 – Unit Masonry iii. 07 9000 – Joint Sealants b. General: i. This contractor shall be responsible for the installation of orange construction fencing along perimeter of staging area and construction to deter pedestrian traffic. ii. Contractor shall submit product data and samples of proposed brick and mortar for comparison to existing. Intent is to match existing as closely as possible. iii. Contractor shall complete an in-place mock-up for review and approval prior to proceeding with the remainder of replacement. iv. All openings created in the building envelope shall be protected with temporary enclosures to protect the building from outside elements. v. All temporary bracing required to complete the scope of this package shall be completed by this contractor. This excludes interior bracing shown on the construction drawings, which will be completed by others. vi. This contractor shall include temporary heating as required for scope of work. c. Masonry i. This contractor shall be responsible for all masonry demolition, including bracing where required for masonry to remain. ii. All lintels and masonry reinforcing will be the responsibility of this contractor. iii. This contractor shall be responsible for all new masonry installations. This shall include, but not be limited to, new brick, and reinforcing. iv. Contractor shall be responsible for all repointing. v. Removal, salvage, and reinstallation of existing stone sills is part of this scope. vi. This contractor shall salvage all existing brick as feasible and mix salvaged brick into new installations. vii. Contractor shall provide new membrane flashings and stainless-steel drip. viii. Contractor shall install all new weeps and ensure existing drainage systems to remain are not impacted by new construction...