Demolition Work - includes removal of trees, brush, vegetation, trash, rubbish, fence, sidewalks, curb and gutter, paving and driveways from the site. Disconnection of utilities; furnishing and compaction of backfill material, furnishing and placing of topsoil; finish grading of disturbed areas; placing and removing safety fencing; seeding; and payment of any permit or disposal fees.; Dry Storage Building Pad and Footings: the cost of constructing the concrete pad, footings, rebar, and joints for the future dry storage building and any other associated work for proper construction.; Linear Storm Sewer Trench Drain. Price includes, but is not limited to, furnishing and installing the linear trench drain including all appurtenances; furnishing and placement of PCC transition; furnishing, excavation, and backfill of discharge pipe; connection to manhole or intake, if required; installation of apron, if required.