**Update 13 May 2024**
Bid Summary dated 13 May 24, Uploaded
The U.S. Corp of Engineers {USACE) has a requirement for road, trail, and infrastructure repairs at
Red Rock lake that includes, but is not limited to, removal of existing aggregate base, preparation
of existing aggregate base, compacted Portland cement or fly ash modified base course, new
compacted aggregate base, compacted aggregate shoulders, topsoil placement, fill, excavation/cut,
asphalt pavement patching, asphalt cement concrete (ACC) milling, asphalt crack/joint sealing, ACC
pavement demolition and removal, saw cut asphalt, trail section replacement, bituminous fog coat,
hot mix asphalt {HMA) binder course, HMA surface course, Portland cement concrete {PCC) milling,
concrete crack/joint sealing, PCC pavement and curb and gutter demolition and removal, steel
reinforcement, concrete curb and gutter, concrete pavements and slabs, PCC sidewalks, synthetic
fiber reinforcement, seeding, geotextile, pavement marking, steel-backed timber guardrail
installation, detectable warning panels, site restoration, and related incidental work.
This action will be and Unrestricted Invitation for Bids (IFB) (Full and Open Competition)
Amendment 0001 was posted 4/29/2024