1 Highway lighting repair at US 61 southbound, mile marker 182.93, gore area of on ramp to US 151 southbound. All wiring to be per National Electrical Code. All material must be new. Price to be bid as lump sum. Itemized list of 30x 8 precast base1 - Valmont DS66-950A336-1515-SLB 40ft mounting height. 2 (Two) - 15 ft mounting arms. 2 (Two) - Phillips roadway RFL180W80LED4K-g2-r3m light head. Wiring as needed; 2. List of materials with individual costs that add up to the line costs. Itemized list of 30x 8 precast base1 - Valmont DS66-950A336-1515-SLB 40ft mounting height. 2 (Two) - 15 ft mounting arms. 2 (Two) - Phillips roadway RFL180W80LED4K-g2-r3m light head. Wiring as needed; 2 Work can be done during the day and not at night. Contractor is responsible for their own traffic control. Contractor will need to close shoulder of ramp (TC202) and right lane, southbound (TC-418) to repair said light pole. Contractor must dispose of all old material. Contractor to grade dirt and shoulder back to original state. Contractor must be registered with the Iowa Division of Labor and be listed on the State's list of traffic Control Technicians. Contractor to provide certificate of insurance per attached terms and conditions. Contractor must supply the state with a complete itemized invoice. A breakdown of labor, parts, materials, equipment usage, Traffic Control, etc.