v1.0 Contractor shall engage necessary engineering to design to code a 73’ wide x 100’ long galvanized truss building, with location-appropriate weather resistance fabric cover. 2.0 Contractor shall perform soil testing to verify location will be able to support new Truss building. 3.0 Upon acceptance of location, Contractor will work with concrete subcontractor to pour required frost footings, full concrete pad and 6’ high concrete walls all around, with the exception of the location of the 14’x16’ wide overhead door and walk-in door on the front of the building. 4.0 Contractor shall provide appropriate Overhead Door and have installed by qualified subcontractor. 5.0 Contractor shall provide appropriate walk-in door and have installed by qualified subcontractor. 6.0 Electrical to building for lights, plug loads and overhead door to be provided by The City.