The scope of work for this project includes the following tasks: 1. Mobilization o Includes all necessary transport, setup, and preparation to complete the project. 2. Pre-cleaning and Inspection o Cleaning the existing 10" pool drain line prior to lining. o Performing an initial inspection to identify potential blockages or damage. 3. 10" CIPP Liner Installation o Installing a 10" cure-in-place pipeline (CIPP) liner within the existing drain line. o Ensuring liner is properly cured and meets all necessary structural and performance standards. 4. Post-cleaning and Inspection o Conducting a follow-up inspection of the lined pipe to verify installation quality. o Cleaning any residual materials from the site. 5. Lateral Line Reinstatement o Reinstating any lateral connections affected by the lining process. 6. Protruding Tap Cutting o Cutting and removing any protrusions within the pipe to ensure smooth operation and flow.