➢ Concrete Slabs: The Contractor shall remove all concrete slabs, asphalt, surface obstructions, masonry slabs, and appurtenances. _______ ➢ There shall not be less than twelve inches (12”) of top soil cover over the entire demolition site. _______ ➢ There shall not be less than twelve inches (12”) of dirt cover over the entire demolition site. _______ ➢ Backfill: When site conditions permit, as determined by the City, on-site soil shall be used as backfill material. The top 12 inches of topsoil shall be stripped and stockpiled on site for use as final topsoil and grading material. The Contractor shall bring in enough topsoil from off-site to place a minimum 12- inch cover on the entire site. Excess excavation materials shall be removed from the site. Topsoil material shall not be permitted as deep fill material. Any borrow or fill material shall be approved by the City before and during the placing of the material. All depressions on the property shall be filled, compacted, and graded to a uniform slope with adequate drainage. _______ ➢ The erection of necessary barricades, walls, fences, etc., for safety of the public shall be the responsibility of the Contractor. NOTE: The Contractor shall provide additional backfill as needed.