Specifications include, but are not limited to: : 1 Mobilization and Demobilization 1 L.S. 2A1 Implementation of the Erosion and Sediment Pollution Control Plan - Rock Construction Entrance - Geotextile Installation 360 S.Y. 2A2 Implementation of the Erosion and Sediment Pollution Control Plan - Rock Construction Entrance - AASHTO #1 Aggregate Placement 160 TON 2A3 Implementation of the Erosion and Sediment Pollution Control Plan - Rock Construction Entrance - AASHTO #1 Aggregate Removal 160 TON 2A4 Implementation of the Erosion and Sediment Pollution Control Plan - Rock Construction Entrance - Geotextile Removal 360 S.Y. 2B1 Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock - Install and Maintain 18" Compost Filter Sock 2,410 L.F. 2B2 Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock - Install and Maintain 24" Compost Filter Sock 200 L.F. 2B3 Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock - Remove Stakes and Cut Open 18" Compost Filter Sock 2,410 L.F. 2B4 Implementation of the Erosion and Sediment Pollution Control Plan - Compost Filter Sock - Remove Stakes and Cut Open 24" Compost Filter Sock 200 L.F. 2C Implementation of the Erosion and Sediment Pollution Control Plan - Rock Filter Outlets 4 EA. 2D Implementation of the Erosion and Sediment Pollution Control Plan - Pumped Water Filter Bag 3 EA. 2E Implementation of the Erosion and Sediment Pollution Control Plan - Orange Construction Fence 200 L.F. 3 Clearing and Grubbing 1 L.S. 4A Access Roads - Access Road 'A' 1 L.S. 4B Access Roads - Access Road 'D' 1 L.S. 4C Access Roads - Access Road 'E' 1 L.S. 5 Access Gate 3 EA. 6 Underground Utility Line Equipment Crossing 10 EA. 7 Temporary Stream Crossing 1 EA. 8A Water Storage Ponds - Pond 1 1 EA. 8B Water Storage Ponds - Pond 2 1 EA. 8C Water Storage Ponds - Pond 3 1 EA. ----- ----- ----- ----- 9B Water Supply - Develop 2018 Drawdown Well Water Source 1 L.S. 9C Water Supply - Develop Valley View Drive Water Source 1 L.S. 9D Water Supply - Water 50,000 PER 1000 GALLONS ----- ----- ----- ----- 11 Fire Fighting Foam 8,000 GALLONS 12A Excavation/Backfilling - Overburden/Quenched Material 1,367,500 C.Y. 12B Excavation/Backfilling - Special Handling of Coal 139,100 C.Y. 12C Excavation/Backfilling - Excavation for Backfilling/Final Grading 755,000 C.Y. 12D Excavation/Backfilling - Alkaline Addition Materials 2,500 TON 13A Blasting - Blasting 559,500 C.Y. 13B Blasting - Pre-Blast Survey 9 EA. 13C Blasting - Post-Blast Survey 9 EA. 14 Drilling Monitoring Boreholes 300 L.F. 15 Steel Casing for Boreholes 300 L.F. 16A Rolled Erosion Control Products - NAG C350 3,900 SY 16B Rolled Erosion Control Products - NAG SC250 1,280 SY 16C Rolled Erosion Control Products - NAG W3000 5,150 SY 17A Seeding - Seed Mixture 1 95 ACRE 17B Seeding - Seed Mixture 2 20 ACRE 17C Seeding - Supplements 115 ACRE 17D Seeding - Mulch 115 ACRE 18 Fence Removal 7,200 L.F. 19 Office Facility 1 L.S. Principal Items of Work and Approximate Quantities: Alternate Bid #1 5 Access Gate 1 EA. 7 Temporary Stream Crossing 1 EA. 9A Develop Marshwood Reservoir Water Source 1 LS 10 Jack and Bore of State Road 1 LS