Specifications include, but are not limited to: This project is being let using the single prime bidding and contracting process.DFD will publicly bid the26applicable mechanical, electrical, plumbing, and fire protection (MEP) divisions of workfirst.Within 527days of the MEP bid opening, DFD will identify a lowest, qualified, responsible, certified bidder in each28applicable MEP division of work. These successful MEP bids must be included in all general prime29contractor bids received. No later than 5 days after DFD identifies the successful MEP bids, DFD will30publicly open general prime contractor bids.General prime contractor bids that do not include the31successful MEP bids will be rejected.The state will enter into a single contract with the lowest, qualified,32responsible, certified general prime contractor and this general prime contractor will enter into subcontracts33with the successful MEP bidders.