The purpose of this amendment is to post RFI questions and answers. Pre-bid RFI Responses VA Medical Center, Leeds, MA Repair Sewer and Bathrooms Building 1 Design-Build Project # 631-23-004 SOW Attachment 1 Project Milestones identifies Phase 1 design documents to be complete at the 10% submission date 45 days after NTP. Does this phase require a complete separate package of 100% documents including specifications? VA RESPONSE: Phase 1 consists of a single room, the Canteen Office. Yes, 100% drawings and specifications pertinent to the canteen office work area will be required. Unedited TIL specifications necessary for the completion of the canteen office may be used for this construction. These specifications are not required to be used for the remainder of the project but may be incorporated. BIM and space planning data are not required for phase 1. According to the included SOW Attachment 1 Project Milestones, Phase 1 does not require any VA review prior to the 10% design submission which requires the Phase 1 100% submission. Is this correct? VA RESPONSE: A less formal review process of the Phase 1 Canteen office is anticipated within the 45 days. This may be accomplished during the weekly or bi-weekly project meetings.