*****UPDATE 18 July 2024*****
The following documents have been uploaded to the attachments section of this notice
- Bid Opening Sign in Sheet
- OF1409 Abstract of Offers
*********** UPDATE 17 July 2024 ************
For anyone unable to attend the bid opening on 18 July 2024, you are welcome to dial in: The dial in information is as follows:
Dial in by phone
571-616-7941
Phone conference ID: 765 603 528#
---------------------------------------------------------------------------------------
*****AMENDMENT 1 - 7/9/2024****
Response deadline extended to 18 July 2024 at 10:00 AM (EST)
The following documents have been uploaded:
- SF 30 (Amendment)
- SF 1442 (Conform copy of the requirement)
- Fire Hydrant Replacement_Statement of Work
The amendment addresses RFIs regarding the period of performance as well as updates to the Bid Guarentee which will need to be adhered to. The Statement of Work has been updated to clarify the priced scope of work for this requirement. The changes to the Statement of Work are as follows:
"Paragraph 5.1.1 Provide all personnel labor, materials, equipment, expertise, and permitting necessary to provide demolition of the existing equipment and installation and commissioning of the new equipment resulting in a fully functional final product in line with the intent of this contract. The scope is to demolish and replace the fire hydrant stem down to the 90 degree bend at the drain valve and make the connection to the existing water line leading to the tapping valve."
additionally, ACM abatement is not included as a requirement for this project.
No other changes to the Statement of Work were made.
------------------------------------------------------------------------------
****UPDATE 7/2/2024****
Hydrant Map & RFi response log have been added to the attachments.
------------------------------------------------------------------------------
****UPDATE 6/26/2024****
Site visit sign in sheet has been added to the attachments.
-------------------------------------------------------------------------------
This notice constitutes an Invitation for Bids (IFB), Solicitation W50S8A-24-B-5208 for Fire Hydrant Replacement at Pease Air National Guard Base (PEASE ANGB), Newington, NH. The Government seeks to award a single firm fixed price contract for services, non-personal, to provide all plant, labor, transportation, materials, tools equipment, appliances and supervisors needed to remove and replace o replace and install thirteen (13) fire hydrants at that location.
The anticipated contract duration shall be approximately 120 days. Please refer to the attached Statement of Work and Drawings attached to this solicitation. Also be sure to review the attached SF1442 for a complete listing of the applicable provisions and clauses. Also please note that the Government is setting this requirement aside as a total 100% small business set aside under the North American Industrial Classification System (NAICS) 237110 which has a small business size standard of $45.0M. The associated PSC code is 4210.
Interested parties shall provide their bids to the Government by the closing date and time of this solicitation and shall be available for public opening on 18 July 2024 at 10:00 EST at the Portsmouth Armory located at 801 McGee Drive, Portsmouth, NH 03801.
Bids shall either be mailed directly to the government at 302 Newmarket Street, Newington, NH 03803 by the time specified in the solicitation or hand carried to the Portsmouth Armory on opening day. The Government cannot accept bids electronically. Interested bidders are strongly encouraged to review the "Instructions to Bidders" in section 00 21 13 of the solicitation.
This posting also constitutes a notice of a pre-bid conference & site visit which the Government will conduct on June 20th, 2024 at 09:00 AM EST on-site at Pease ANGB. Please review 00 21 13 for instructions and submission requirements for site access before the event.
In accordance with FAR 36.211(b), the following information is provided:
(1) The National Guard has no agency-specific policies or procedures applicable to definitization of equitable adjustments for change orders under construction contracts other than those described at FAR 43.204, DFARS 243.204 and AFARS 5143.204.
(2) Data for the prior 3 fiscal years regarding the time required to definitize equitable adjustments for change orders under construction contracts for the National Guard is currently not available, but will be compiled and provided in future announcements