Solicitation W9128F24B0022 is cancelled and an award will not be made from this solicitaiton.
***Amendment 0001 has been uploaded to Attachments Section below with the updated ProjNet Bidder key.***
Oahe Dam - Rehabilitate Spillway Apron Slab.
The Contractor shall selectively demolish existing concrete slabs and walls of the spillway as defined in the specifications and drawings. The Contractor will form, reinforce, pour and cure concrete patches to replace the demolished concrete, which may include the installation of waterstop at the joints. Two 6" check valves in the spillway gallery that act as a flood overflow will be replaced, and the short piece of connection pipe will be repainted.
The magnitude of Construction is $250,000.00 - $500,000.00. This requirement will be a 100% Small Business Set-Aside.