Questions and Answers posted on 31 October 2024
_________________________________________________________________________________________________
Amendment 0003 posted on 31 October 2024
See formal SF30 Amendment titled "6973GH-24-R-00212 Amendment 0003" in the attachments/links section. This amendment makes changes to the solicitation as detailed on page 1 of the amendment which states:
The purpose of Amendment 0003 is as follows:
1) Extend the due date from 31 October 2024 at 1700 CT to 08 November 2024 at 1700 CT.
2) All other terms and conditions remain unchanged and in full force and effect.
All offerors are required to acknowledge Amendment 0002 on page 2 of the SIR or provide a signed copy of the amendment (SF30) with their bid submission. If this amendment is not acknowledged or signed, the bid will be considered non-responsive.
Note: The FAR references cited in SAM.gov are not applicable to the Federal Aviation Administration (FAA) as the FAA has its own policies and guidance referenced in the Acquisition Management System (AMS).
________________________________________________________________________________________________________
Amendment 0002 posted on 18 October 2024
See formal SF30 Amendment titled "6973GH-24-R-00212 Amendment 0002" in the attachments/links section. This amendment makes changes to the solicitation as detailed on page 1 of the amendment which states:
The purpose of Amendment 0002 is as follows:
1) Extend the due date from 18 October 2024 at 1700 CT to 31 October at 1700 CT.
2) All other terms and conditions remain unchanged and in full force and effect.
All offerors are required to acknowledge Amendment 0002 on page 2 of the SIR or provide a signed copy of the amendment (SF30) with their bid submission. If this amendment is not acknowledged or signed, the bid will be considered non-responsive.
Note: The FAR references cited in SAM.gov are not applicable to the Federal Aviation Administration (FAA) as the FAA has its own policies and guidance referenced in the Acquisition Management System (AMS).
________________________________________________________________________________________________________
Questions and Answers posted on 08 October 2024
_________________________________________________________________________________________________
Amendment 0001 posted on 01 October 2024
See formal SF30 Amendment titled "6973GH-24-R-00212 Amendment 0001" in the attachments/links section. This amendment makes changes to the solicitation as detailed on page 1 of the amendment which states:
“The purpose of Amendment 0001 is to extend the due date from 01 October 2024 at 1700 CT to 18 October at 1700 CT. All other terms and conditions remain unchanged and in full force and effect.”
All offerors are required to acknowledge amendment 0001 on page 2 of the SIR or provide a signed copy of the amendment (SF30) with their bid submission. If this amendment is not acknowledged or signed, the bid will be considered non-responsive.
Note: The FAR references cited in SAM.gov are not applicable to the Federal Aviation Administration (FAA) as the FAA has its own policies and guidance referenced in the Acquisition Management System (AMS).
________________________________________________________________________________________________________
Original Post
The Federal Aviation Administration (FAA) has a requirement for the refurbishment or replacement of the parking lot, curbs, gutters, and sidewalks for the TOWB at Savannah Hilton Head International Airport, in Savannah, GA.
It is anticipated that a stand-alone contract with Firm Fixed-Price pricing arrangement will be awarded as a result of this solicitation. The NAICS code applicable to this requirement is 236220. The business size standard for this NAICS is $45M.
Contractors must be registered with the System for Award Management (SAM,) www.sam.gov on the date established for receipt of offers. Reference AMS Clause 3.3.1-33, paragraph (d), "if the offeror does not become registered in the SAM database in the time prescribed by the Contracting Officer, the Contracting Officer may proceed to award to the next otherwise successful registered Offeror." The FAA reserves the right to review and verify each offerors program eligibility. Potential offerors should note that the FAA reserves the right to communicate with one or more offerors at any time during the SIR process. This SIR/RFO is not to be construed as a contract or a commitment of any kind. The Government shall not be liable for payment of any costs attributed to the preparation and submission of proposals.
This project is intended to be funded by the Bipartisan Infrastructure Law (BIL). As such this project will be subject to associated FAA reporting requirements. If a contract is awarded, the contractor will be responsible for associated reporting requirements on a quarterly basis and prior to final payment per the associated contract clause AMS 3.18-1 Bipartisan Infrastructure Law – Reporting Requirements (October 2022) that will be included in any resulting solicitation and contract. A copy of this clause and report form titled “Uniform Bipartisan Infrastructure Law (BIL) Data Report” are available in the attachments of this announcement.
All questions regarding the project/specifications/plans must be received in writing (Samantha.A.Pearce@faa.gov) no later than 3:00 p.m. CT, 1 week prior to the closing date to allow for responses to be provided prior to due date for receipt of proposals.
Per 3.2.2.3-63 SITE VISIT (CONSTRUCTION) (JUL 2004), a site visit is scheduled for 16 September 2024 at 1000 EST at SAV ATCT 100 Melaver Dr., Savannah, GA 31408. On-site POC: Johnathan Timms (904)318-2362 or Tommy Hughes (803)240-3207. Provide the name of attendees to the Contracting Officer four (4) days prior to Site Visit. Attendees are encouraged to perform a self-wellness check prior to arriving and social distance while on-site when possible.
Any responses received after the time specified may not be considered in accordance with AMS Provision 3.2.2.3-14, Late Submissions, Modifications, and Withdrawals of Submittals, incorporated by reference in the solicitation. If all requested information is not furnished, the vendor's response may be determined ineligible.