Update 10/18/2024: QA_10-18-2024.pdf posted to attachments.
Update 10/18/2024: Due to technical error, some physical data files did not upload when the solicitation was initially posted. The remaining physical data files are available under Physical Data_2.zip.
PROJECT: MT FLAP BOR 2980(1), Sun River Bridge Replacement
LOCATION: 50 miles NW of Augusta, MT
WORK: The work consists of building a new bridge about 200 feet downstream of the existing bridge, with new approach. The approaches are on embankments and MSE wall approaches. Final surfacing will be gravel for approaches and concrete on the bridge.
The project includes construction of a 3 span, 462-foot long precast-post-tensioned girder bridge with a precast concrete deck. Abutments are founded on both spread footing and piles within an MSE wall fill. Piers are supported on 10 foot diameter drilled shafts. The work may include as an Option demolition of the existing steel truss bridge upon completion of the new structure.
LENGTH: 0.36 miles
TENTATIVE COMPLETION DATE: Fall 2026
CONTRACT TYPE: Sealed Bid, Firm-Fixed-Price
ESTIMATED PRICE RANGE: Between $10 million to $20 million
INTERESTED VENDORS LIST: To view the Interested Vendors List, you must register as a SAM user, be logged in, and linked to an entity. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in SAM.gov. If you need assistance, call the Federal Service Desk at 866-606-8220.
THIS SOLICITATION IS OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS