AMMENDMENT 001: The purpose of this ammendment is to revise the PWS to Version 3, Please see attached. The period of performance will also change to 4 months, approximately March until June.
The contractor shall provide all labor, materials, equipment, and supervision necessary to erect scaffolding around the digester flare pipe, extending to the roof of the penthouse facility. The scaffolding shall be designed, installed, and maintained in accordance with OSHA regulations and industry best practices. The scaffolding will remain in place for approximately 4 months, from March 2025 to June 2025. The contractor shall also provide periodic safety inspections of the scaffolding throughout this period. At the end of the period, the contractor shall tear down the scaffolding and remove all material and equipment provided.
Please refer to Performance Work Statement (PWS) attached. There are also further details in the Q and A document.