Specifications include, but are not limited to: Parcel 1 – 3721 North 13th Street – 2-story frame 2-family dwelling Remove dwelling, fences on the west side of the lot, garage slabs, sidewalks, concrete steps, trees, bushes and shrubs. Contractor shall be responsible for removal of all tree stumps on this parcel as part of the demolition. Prior to demolition, the contractor must meet at the site with the Condemnation Inspector to provide a demolition plan. Contractor must also notify neighbors on the block face of the demolition that demolition activity is about to begin. This notification shall be done via a department-approved letter or door knocker. The inspection report from Harenda Management Group is included. BID PRICE MUST INCLUDE THE PROPER REMOVAL AND DISPOSAL OF ANY ASBESTOSCONTAINING MATERIALS OR ANY OTHER HAZARDOUS MATERIALS LISTED IN THE REPORT FROM HMG REQUIRED TO BE ABATED BEFORE MECHANICAL DEMOLITION. (5 days to complete) Parcel 2 – 2860 North 16th Street – 2-story frame 2-family dwelling Remove fire-damaged dwelling, fences, sidewalks, concrete steps, railings, trees, bushes and shrubs. Prior to demolition, the contractor must meet at the site with the Condemnation Inspector to provide a demolition plan. Contractor must also notify neighbors on the block face of the demolition that demolition activity is about to begin. This notification shall be done via a department-approved letter or door knocker. The inspection report from Harenda Management Group is included. BID PRICE MUST INCLUDE THE PROPER REMOVAL AND DISPOSAL OF ANY ASBESTOSCONTAINING MATERIALS OR ANY OTHER HAZARDOUS MATERIALS LISTED IN THE REPORT FROM HMG REQUIRED TO BE ABATED BEFORE MECHANICAL DEMOLITION. THE INSPECTOR FROM HMG WAS UNABLE TO GAIN ACCESS TO ALL AREAS OF THE BUILDING DUE TO THE FIRE DAMAGE. ON SITE MONITORING BY A CERTIFIED ASBESTOS SPECIALIST WILL BE REQUIRED DURING DEMOLITION. THIS COST IS TO BE INCLUDED IN THE BID PRICE. (5 days to complete) Parcel 3 – 3617 North 20th Street – 2-story frame 2-family dwelling Remove fire-damaged dwelling, fences, garage slabs, sidewalks, boat, bushes and shrubs. Contractor shall be responsible for removal of all tree stumps on this parcel as part of the demolition. Successful contractor must obtain a demolition permit for the previously razed garage at the site (4,000 cubic feet). Prior to demolition, the contractor must meet at the site with the Condemnation Inspector to provide a demolition plan. Contractor must also notify neighbors on the block face of the demolition that demolition activity is about to begin. This notification shall be done via a department-approved letter or door knocker. The inspection report from Harenda Management Group is included. BID PRICE MUST INCLUDE THE PROPER REMOVAL AND DISPOSAL OF ANY ASBESTOSCONTAINING MATERIALS OR ANY OTHER HAZARDOUS MATERIALS LISTED IN THE REPORT FROM HMG REQUIRED TO BE ABATED BEFORE MECHANICAL DEMOLITION. THE INSPECTOR FROM HMG WAS UNABLE TO GAIN ACCESS TO ALL AREAS OF THE BUILDING DUE TO THE FIRE DAMAGE. (5 days to complete) Parcel 4 – 3602 North 25th Street – 2-story frame 2-family dwelling & 1-story frame garage Remove dwelling and garage, garage slabs, fences, sidewalks, concrete slabs, bushes and shrubs. Contractor shall be responsible for removal of all tree stumps on this parcel as part of the demolition. Prior to demolition, the contractor must meet at the site with the Condemnation Inspector to provide a demolition plan. Contractor must also notify neighbors on the block face of the demolition that demolition activity is about to begin. This notification shall be done via a department-approved letter or door knocker. The inspection report from Harenda Management Group is included. BID PRICE MUST INCLUDE THE PROPER REMOVAL AND DISPOSAL OF ANY ASBESTOSCONTAINING MATERIALS OR ANY OTHER HAZARDOUS MATERIALS LISTED IN THE REPORT FROM HMG REQUIRED TO BE ABATED BEFORE MECHANICAL DEMOLITION. (5 days to complete) Parcel 5 – 2826 North 27th Street – 1-story frame 1-family dwelling & 1-story frame garage Remove fire-damaged dwelling and garage, fences, garage slabs, sidewalks, concrete steps, railings, trees, bushes and shrubs. Prior to demolition, the contractor must meet at the site with the Condemnation Inspector to provide a demolition plan. Contractor must also notify neighbors on the block face of the demolition that demolition activity is about to begin. This notification shall be done via a department-approved letter or door knocker. The inspection report from Harenda Management Group is included. BID PRICE MUST INCLUDE THE PROPER REMOVAL AND DISPOSAL OF ANY ASBESTOSCONTAINING MATERIALS OR ANY OTHER HAZARDOUS MATERIALS LISTED IN THE REPORT FROM HMG REQUIRED TO BE ABATED BEFORE MECHANICAL DEMOLITION. (5 days to complete)