Specifications include, but are not limited to: Prior to undercutting or excavating below subgrade (EBS) or placing any Dense Grade Base (See Section 32 11 23.33), contact the University Project Representative to schedule inspection of the subgrade and proof rolling of the subgrade. All proof rolling shall be completed in accordance with the requirements of the paragraph entitled ‘Quality Assurance’ and shall meet the criteria as defined below. To complete proof rolling, entire pavement subgrade shall be provided with a relatively smooth surface, suitable for observing soil reaction during proof rolling. Contractor shall schedule and provide a fully loaded tri-axle dump truck for proof – rolling. Loaded truck shall have a minimum gross operating weight of 30 tons. Test shall be conducted with “tag” or “pusher” axles retracted from the ground. Proof rolling shall be accomplished in a series of traverses parallel to the centerline of the driveway, street, or parking area. The truck shall traverse the length of the street or parking area once for each 12’ of width at speeds less than 5 mph. Additional passes along the traverse shall be completed as directed by the University Project Representative to further define unsatisfactory subgrade.