Furnishing and installing 800 LF of 10-inch C900 PVC pressure sewer along Riverside Drive to Bank Street Extension including fittings and interconnections to the existing system. The project also includes installing 85 LF of 12-inch TR Flex DI pipe under the Packard Bridge. The City of Lebanon has pre-purchased the TR Flex DI pipe and the pipe is stored at the Lebanon Wastewater Treatment Plant. The Contractor will be required to pick up the pipe at the Wastewater Treatment Plant. The existing pressure sewer shall remain in service to provide continuous service until the new pressure sewer is constructed, pressure tested, and ready for service. At that time, the system will be shutdown, the interconnections shall be made, and the pressure sewer will be placed back in service.