Specifications include, but are not limited to: Completion of approximately 445 linear feet of 5 foot wide sidewalk on Hobbs Farm Road located in Wells, Maine. The major elements of proposed work under this Contract include: 1. Maintaining safe conditions: traffic control, Dig Safe, access to private property; 2. Coordination with the Town of Wells; 3. Preparing and supplementing the crushed aggregate base course (approximately 355 LF); 4. Installing the bituminous pavement (approximately 355 LF); 5. Installing 7 tip downs; 6. Adjusting catch basin rims as needed; 7. Adjusting pavement at catch basins for drainage as needed; 8. Adjust surrounding grades as needed for drainage; 9. Erosion control measures (BMP’s); 10. Loam and seed all disturbed areas; 11. Re-set boulders at CB 13224; 12. Install a 3” caliper maple tree in front of Lot 12; 13. Install guy wire covering in front of Lot 13; 14. Install rip rap apron at end of sidewalk; and 15. Clean up following completion of the work.