Specifications include, but are not limited to: The project will consist of one main line item with total amount for scope of work items. Vendors must submit a bid for the one main line item including all six areas under the scope of work. The one main line item is for: removal of existing damaged piping; installation of new pipe; concrete and fence work; finishing; warranty; site clean-up. 1. **Removal of Existing Damaged Piping**: Removal of 660' (area A) and 230' (area B) of damaged HDPE ADS N-12 Pipe. (Area A is by the south side of the football field and Area B is at the drive on the North side of the school). 2. **Installation of New Pipe** Install new Aluminized CMP pipe matching size that in the areas of demolition. Add one new #10 inlet and tie-ins to existing inlets as needed. Backfill with sand and dirt. 3. **Concrete and Fence Work** Remove and replace concrete walks, curbs, and chain link fence in the path of the work.