Specifications include, but are not limited to: 1. Repair of concrete beams and overhead slab in Area E basement, including strengthening of the existing beams with CFRP wrap. 2. Construct CMU containment wall and fill the west side of Area E basement with cellular fill. 3. Install vertical reinforcing in existing exterior CMU walls at Areas B, D, F, and G, which includes grouting the reinforced cells and dowelling into the existing wall foundations. 4. Install steel braces at top of existing exterior CMU walls at Areas B, D, F, and G and install adhesive anchors along the length of the steel braces. 5. Protection of stored materials from dust, debris, and weather. 6. Contractor and his/her subs shall comply with OSHA and MSD safety requirements (See Drawings) at all times any work is done at site. All correspondence must be made through the Vendor Portal.