The Scope of Work for the Project includes lining existing sanitary sewer pipe and existing manholes. Approximate quantities are: 515 LF of 14” diameter pipe, 229 LF of 12” diameter pipe, 5,258 LF of 8” diameter pipe, 131 LF of 6” diameter pipe, and 59.3 VF of manhole lining. Lining shall be cured-in-place pipe (CIPP) using a resin-impregnated fiberfelt tube. The work includes cleaning and video inspection of the sanitary sewer pipe before lining. Work shall include traffic control, restoration and all other incidental items and work described in the Drawings, Specifications and/or other Contract Documents or reasonably inferable therefrom. The project is funded through the Jefferson County Community Development Block Grant program, CDBG# SI-23-002. The City anticipates issuing a Notice to Proceed once grant approval is received from the CDBG program, with the anticipated start date to be September 2024 dependent on weather.