. This project consists of the demolition and installation of a new furnace and AC unit to replace the existing one. Testing and balancing of existing system to be included. A new 100A Subpanel surface mounted with a 100A 2 pole breaker in existing panel to feed subpanel is to be installed with a new raceway and wiring between panel. Furnish and install new casework, flooring, painting, HVAC, plumbing, and electrical as shown or specified within the bid documents. Reference each bid package scope of work for complete scope of work narrative. This project has 7 (Seven) alternates. This project is anticipated to be bid and awarded in September 2024, material procurement to immediately follow once contracts are issued, and work will occur in the fall of 2024. The anticipated start date is October/November 2024.