Provide a high quality, cost- effective structured cabling system for this project. Please refer to EXHIBIT A (separate document) for drop and IDF locations. Included in this project are 35 access point drops, 47 camera drops, and 30 data drops for 118 total. There are also two fiber runs between data closets. There is one fiber run (24 strands) from the existing district MDF (800 Madison Street) to the new Agricultural Center. The fiber run will have enough capacity for the Agricultural Center PLUS two additional planned structures. The distance is approximately 650 feet. The fiber will be buried under the roadway and wherever possible for the full distance. For the fiber connection to the new facility, 4" conduit with two, 3-cell maxcell innerduct required.