Specifications include, but are not limited to: The project consists generally of the construction of one 1,000 gallon per minute raw groundwater supply well adjacent to an existing water treatment facility, including all drilling, test well development, raw water analysis, reaming, casings, screen, gravel wall, well development, well testing, well cleaning, CCTV inspection, construction of pump foundation, well pump, discharge head, column assembly, shafts, suction pipe, electric motor, water level indicator, pressure gauge, discharge piping, check valves, flow meter, gate valves, insulation, connection to the existing raw water line, painting, electrical and controls, site work, fencing, site restoration, final cleaning, and all other necessary and appurtenant work required to complete the work as described in these specifications and detailed in the drawings.