Specifications include, but are not limited to: The Macomb Readiness Center requires two (2) boilers to be replaced to restore hot water and heat to the facility. 1.2.1. Vendor to provide all materials and labor to replace boilers per the terms of this contract. 1.2.2. Remove and properly dispose/recycle existing LES Inc. Model HW3-30 Boilers (2) including gas, water, power, venting, as required. 1.2.3. Remove and properly dispose/recycle existing Power Flame Model JR30A-12 Gas Burners (2). 1.2.4. Remove and properly dispose/recycle existing 2 HP 100 GPM Boiler Pumps. 1.2.5. Furnish and install two condensing boilers containing the minimum standards listed below. 1.2.5.1 1200 MBH input. 1.2.5.2 1000 MBH output. 1.2.5.3 Entering Water Temp 160°F. 1.2.5.4 Leaving Water Temp 180°F. 1.2.5.5 Working Pressure: 30 PSI.