1. Work is expected to begin within 10 days of the official “Notice to Proceed” and all work be completed within 60 calendar days. 2. Scheduling: Contractor shall submit a schedule of work to be performed two (2) weeks in advance (e.g. a two week look ahead) 3. Hardware and labor costs to replace signage shall be included in the sign costs on the attached Bid Schedule. 4. The contractor shall keep vehicles, trailers, or other equipment on the street pavement and coordinate any flagging or other traffic control activities. 5. Any areas damaged by the contractor shall be restored to the condition existing immediately prior to the contractor mobilizing to the work area within 7 days of the damage 6. GDOT approval will be necessary for all work on State routes. 7. The Contractor is responsible for coordinating with adjacent property owners, if applicable, regarding irrigation systems and landscaping. Damage incurred to irrigation systems or landscaping shall be the responsibility of the Contractor. No claims will be considered for extra compensation. 8. The City of Doraville does not warrant or guarantee the accuracy of the quantities or sign codes depicted within this bid. The contractor is responsible for the verification of all quantities and sign codes prior to submittal of their bid. 9. Any item which must be removed during the construction work and is not specially called for shall be removed by the Contractor. The cost shall be included in the unit cost for the bid items. No claims will be considered for extra compensation. 10. It is the intent of this contract for each unit price bid to include all labor, materials, equipment, tools, transportation, traffic control, police presence, flagging, supplies, etc., as necessary, to complete the work in accordance with the contract documents. No additional unit costs shall be allowed for clearing, grubbing and/or grading activities unless otherwise specified.