1) 4" SDR 11 PE 2406/2708 Polyethylene Line Pipe LF 5500 2) 2" SDR 11 PE 2406/2708 Polyethylene Line Pipe (includes two 2” anodeless risers and meter valves) LF 1500 3) 4" Poly-Ball valves and valve boxes EA 3 4) 2" Poly-Ball valves and valve boxes EA 3 5) Regulator station (includes tie-in to existing 6” steel main, one 2” ball valve with valve box and a minimum of 25’ of 2” steel) EA 2 6) Meter Set EA 1 7) Rock bore addition to Items 1 above LF 100 $100 $10,000 8) Pad Material/Clean Fill LF 50 $5 $250 9) Hard Surface Haul-off SQ FT 50 $4 $200 10) Type C Silt Fence LF 500 $3 $1500 11) Hay Bales (staked) EA 20 $10 $200 12) Tree Protection and Buffer Delineation Orange Fencing LF 25 $3 $75 13) Per foot of Extra Depth where required LF 50 $10 $500 14) Solid Rock Excavation CY 10 $200 $2000 15) Asphalt/concrete replacement SQ FT 10 $15 $150