1. Select grubbing of the existing water line alignment within the easement. 2. Install erosion control. 3. Excavation and trenching, directional drilling to grade. 4. Installation of all HDPE water line piping, valves, tees, elbows, meters, and associated appurtenances. Minimum water line depth shall be 30 inches, following profile of existing to maintain gravity flow. The new water line for ODFW will be continuous from the water storage tank to the existing valve box location as noted on the Drawings. The water line for the Summer Lake Resort will be continuous from the storage tank to the existing valve location as noted on the Drawings. This line will also have a tee installed for water service to two (2) residences. Both water lines will be installed in sleeves where crossing of the irrigation ditches and the highway is required. 5. The existing water line will be capped, and left in place; and decommissioned only after successful testing of the new water lines.