• Remove and dispose of all Category I, Category II and RACM materials and Universal Wastes listed in the Pre-demolition Inspection Report dated June 2024. ANY EXTERIOR WINDOWS OR DOORS THAT ARE REMOVED DURING THE ABATEMENT MUST BE BOARDED. • Raze and remove all debris from structures and parcels, including any footings, basement walls and floors • Remove private concrete pavement and walkways surrounding buildings • Remove and replace any sidewalks and curbing marked by City • Remove concrete driveway approaches and replace approaches with concrete curb and gutter • Remove and stump all trees, stumps, scrub trees and brush • Remove and cap at curb the sanitary sewer and water laterals. PLEASE NOTE: The location of the sanitary sewer and water laterals is not always accurate. Bidders should be prepared to “camera” the sanitary sewer laterals to determine exact location • Backfill, grade and seed site after razing in accordance with general specifications and Erosion Control Plan • Obtain necessary Federal, State and local permits