The project generally includes repairing damage incurred during the June 2022 Flood event to the Billings Water Treatment Plant Intake #2 Catwalk and Building. The project is utilizing insurance, FEMA disaster funds, and FEMA hazard mitigation funds to bid a single project that will mitigate future hazards. The project generally consists of replacing and lifting the catwalk and building by approximately 5 feet, including structural rehabilitation; demolition; construction of a new precast building; and process, mechanical, and electrical improvements. Base Bid Schedule No. 1 includes demolition of existing facilities, including the existing intake building, existing electrical conduits and conductors, and removal of the existing catwalk bridge deck. Demolition will require lead and asbestos abatement.