The scope of this project includes, but is not limited to the activities listed below for the concrete slab replacement 2.2.1 Demolition and dispose of existing concrete slab at the Fueling Station. The existing concrete slab to be demolished is 6” thick. 2.2.2 Cautiously remove additional base/subbase material as needed. 2.2.3 Rework and compact the existing subgrade and base material. 2.2.4 Frame and install steel reinforcement in proposed new concrete area. 2.2.5 Pour approved concrete mix unto the proposed concrete area. The proposed slab shall be 10.5” thick as per Exhibit B, sheets S1.00 and S2.00. 2.2.6 Perform the concrete crack repair as identified in Exhibit B – Structural Plans. 2.2.7 Re-paint metal faces of curbs & bollards.