The guzzler tanks are solid fiberglass tanks that weigh approximately 800 lbs. Three locations will need tanks flown in. Two locations already have tanks on-site. The second load consists of roofing materials and metal posts that must be lifted to each site to build aprons that also weigh approximately 800 lbs. This load will be for all five locations. A third load of wood fencing materials weighing approximately 800 lbs will be flown into three locations. In total with the guzzler tanks and materials, the helicopter will need to take three trips each for three guzzler sites, and one trip each for two guzzler sites. There will be 11 loads or trips needed to get the tanks and materials to the desired sites. The helicopter crew will also be responsible for attaching tanks and materials to the helicopter to be lifted off and to be at the drop-off locations to detach the materials from the helicopter. The helicopter crew could have members hike into staging areas instead of being flown in, but that will be up to the contractor to decide.