Bidding Requirements 1. Delete and replace the following text in specification Section 00800 Supplementary Conditions: a. SC-12.01 Article 12.01 B.1 – delete 365 Calendar Days and replace with 180 Calendar Days. 2. Add following text to specification Section 01015 Specific Project Requirements: a. Part 1 – General – Paragraph 1.09 Sequence of Work – add Subparagraphs 1a & 1b, insert above Subparagraph 1. 1a. Water Main Replacement Contractor shall coordinate sequence of work with Roadway Improvements Contractor (aka., “Coordinating Contractor). See Section 00800 Supplement Conditions SC-7.02A for additional information. 1b. Water Main Replacement Contractor shall begin work on the eastern most end of the project area (e.g., intersection of Topping Ave. and Front Street) and progress westward along Front Street toward Chouteau Trafficway. At least one crew shall be actively working on Front Street at all times during normal business hours until substantial completion for work along Front Street has been achieved.