1) Install water and sewer utilities to the building. b. Renovate the first floor of existing warehouse to include the IT Repair Area (A115),IT Storage Area (A-121), Staging Area (A122), Restrooms (A-110,A-113, A111, A-114), Janitor Closet A-112, and the Network Equipment Room (A-109). Restroom fit out will be a part of Option 1. Furniture and storage items associated with the IT areas will be part of Option 2. c. Construct a new mezzanine, approximately 6,000 square feet, that includes, foundations through existing first floor concrete slab, structural framing, metal beams, metal deck and elevated concrete slab, metal stairs and railing assemblies. Mezzanine furniture and storage equipment is excluded from this scope. d. Demolition of existing materials, except for existing Prefab Office E-101. e. Salvage existing materials where noted for reinstallation in renovated building.