The Project consists of furnishing all labor, materials, tools, equipment and incidentals necessary for construction of a potable water booster pumping station at 10 Busch Drive in Cartersville, Georgia, including: a precast concrete metering vault, precast concrete double check valve vault, a masonry pump station building, three 200 hp horizontal split case pump swith VFD’s, three 8-inch pump control valves, a 16-inch magnetic flow meter in precast concrete vault, a 5 ton travelling bridge crane, all with associated piping, fittings, electrical and controls, and other appurtenances, including, but not limited to site grading, erosion control, asphalt paving, site fencing, grassing and landscaping, testing, flushing, disinfection, start-up, and all related work for a complete and operational facility.