1. Subcontractor is responsible to check approved plans and soils report. 2. Flatwork shall be 4” thick Type II/V (P.S.I per plan) per CBC. 3. Design as shown on the approved site plans. (Including all AC Pads). 4. Including parking lot: All concrete curb, gutter, truncated domes and walkways. 5. All prep work as shown on the plans. 6. Owner will provide street permit, third party testing and surveying for Offsite/Onsite. 7. Shall include offsite improvement: Saw cut, demo and construct new street sidewalk. 8. Pour concrete per plan. Asphalt by others 9. All pumping shall be included in the contract price. 10. No calcium chloride or additives to be used without prior written authorization from Owner. 11. Subcontractor is responsible for providing generator. Owner will not provide temp power on site(s).