The Contractor shall be responsible for: 1. Verification of dimensions and conditions at the project for the display and control equipment locations prior to ordering/manufacturing. 2. Submittal of State registered structural stamped designs and calculations with the shop drawing submittals. This will be for the final connection from the provided steel tubing to the display only. 3. Provision of all transportation and hoisting. 4. Furnish protective covering during construction/installation to prevent damage or entrance of foreign matter. 5. Replace at no expense to Owner/project, product damaged during delivery, storage or handling. 6. Provision of safe and protected storage. The owner takes no responsibility for damage or theft relating to negligence in failure to secure equipment by The Contractor.