The Work of this Contract is generally described as general construction of wastewater treatment facility buildings and basins including sitework, structural, architectural, UV equipment, electrical, and instrumentation and control. The Project includes the following: Removal of three individual channel mounted UV systems. Including, three UV banks, three power distribution centers, and three hydraulic system centers at Structure 140. Prepare existing channel walls to conform with the new depth and dimensions of the UV Banks as noted in the drawing set. Install a new Owner Furnished 480 volt power panel and transformer serving the UV System. Install new Owner Furnished UV Disinfection equipment. Remove and replace the scum baffles, v-notch weirs and troughs at Final Clarifier No.1 and No. 2 at Structure 130. Remove and replace three motor operated gates.