a. General KCDC will pay attention to finishing and curing, asshould the supplier. Concrete that is not properly finished and/or cured will not be accepted. Therefore, the supplier will: 1. When finishing concrete, ensure that the surface is not finished until after the bleed water has risen. Do not “Bless” the concrete when finishing. Both practices will all but guarantee surface failures. 2. Use two applications of curing compound and the surface should appear uniform in color. If the concrete appears splotchy, not enough compound has been applied. 3. In the process of removal and replacement of existing concrete and/or installation of new concrete, tree root growing under the existing concrete are often encountered and must be removed. Saw cutting the tree root to provide a clean severance from the main tree root system will be used to remove root(s) that are impeding the installation of the replacement concrete work or new concrete work. Any voidsremaining afterthe roots have been removed will be filled and compacted using Crusher Run.” The cost of saw cutting and removal of the tree root(s) will be incidental to the various concrete pay item(s). 4. The supplier shall furnish all labor, materials and equipment to place, finish, protect and cure fresh concrete. Methods and materials shall conform to state and local building code requirements in particular those requirements referenced in the BOCA Code including American Concrete Institute (ACI), Portland Cement Association (PCA), American Society of Testing and Materials (ASTM) and other references. b. Concrete Curb and Gutter Furnish all labor, materials and equipment to install new curb and gutter per standard specifications. Dispose off‐site all excavated materials. The suppliershall provide the work necessary to ensure all materials adjacent to the new construction edges shall be neat and conform to the type of materials existing prior to construction. c. French Drain Furnish all labor, materials and equipment to install new French Drains and remove and dispose of all unused excavated materials offsite. The supplier shall be responsible to ensure that French Drains are constructed in such a way that adequate 21‐A stone bedding and compaction is provided. French Drainsshall be bedded in at least twelve inches of No. 57 stone with the stone and drain completely incased in an acceptable geotextile fabric. The supplier shall provide the necessary work to ensure all materials adjacent to new construction edges shall be neat and conform to the type of materials existing prior to construction.