1. The following specifications detail medium voltage cable for use on the 12,470V campus primary distribution system. The cable will be installed in concrete encased duct bank by others. The following specification covers the construction requirements of the cable to be furnished Cable to be delivered on wooden reels cut to lengths specified prior to ship date. It is anticipated approximately 24 cuts will be required. Delivery will be accepted on or after May 6, 2025. Delivery of all materials must be received by Clemson University no later than 40 weeks from the issue of the purchase order to the contractor. 2. Contractor must adhere to delivery deadlines. Clemson University reserves the right to cancel the contract and/or impose penalties for missed deadlines. a. A penalty of 0.5% (zero point five percent) of the total contract value shall be applied for each calendar day beyond the agreed delivery date as specified in Section III Scope of Work/Specifications A, 1. of this contract. This penalty will begin accruing on the first day following the missed delivery date and shall continue until delivery is completed or the contract is terminated, subject to a maximum cumulative penalty of 10% of the total contract value.