Specifications include, but are not limited to: The Technology upgrade is generally described as: Technology and data upgrades that include but are not limited to the demolition of the existing MDF in room 03A and the existing IDF-LIB located in the Bungalows. A new MDF build-out in storage room 22A and a new outdoor exterior IDF build-out near the Bungalows, with additional electrical work to accommodate expansion; new data drops, network equipment and connections to accommodate expanded technology requirements affecting the main building, classrooms, administrative offices, corridors, other service areas; installation of data and phone network equipment and systems; network racks and equipment with associated conduit, cabling, fiber, electrical wiring, and panels; and, demolition and removal of abandoned equipment and materials, hazardous materials removal.