● Base bid should include the following abatement of approximately 3,200 SF of carpet, VCT, mastic, and base as shown in GREEN and PINK on the attached floor plan: o Classroom 131 - 1,455 SF (remove carpet, tile, mastic, and base including closet, restroom, and office) o Classroom 134 - 1,320 SF (remove carpet, tile, mastic, and base including closet, and restroom) o Corridor (at entry #4) - 425 SF, including both sets of stair treads and stage landing (remove tile, mastic, and base including stair treads, leave non slip nosings) ● Remove vinyl base in locations where flooring is abated. ● File all necessary permits and maintain records in accordance with DNR abatement requirements. ● Coordinate with Hawkeye Environmental related to permits, abatement plans, clearances, etc. ● Protect school property from damage. Any damage by the contractor shall be reported to the project manager and repairs shall be made immediately at the contractor’s expense. ● Perform necessary cleaning at the end of each day (per abatement plan) to ensure a clean and safe work area. ● Contractors may schedule a pre bid meeting with the Construction Project Specialist prior to bidding the project