This project scope includes the phased replacement of the three existing generators serving the UMMC, including: Removal of one existing generator to make room for a new 13.2kV, 2MW emergency generator to feed the existing 13.2kV switchgear serving the North Hospital and modifications to the existing paralleling switchgear to accommodate controls and synchronization. Removal of two existing generators and replace with two 480V, 2.0 MW emergency generators and refeed to the existing paralleling gear. The three replacement Gensets shall be EPA Emissions Certified for Stationary Emergency Use Only (former Tier 2). In addition to the requirements of the enclosed drawing and specification, the scope of work must include but not be limited to the following: Outage Coordination with the UMMS and UMMC Facilities Team Refeeding and modifications to the existing paralleling gear as required to make the emergency power system operational Schedule Coordination with the construction of the UMMC Stoler CAM project and other hospital operations Storage of Gensets prior to delivery to the project site and installation...