General Description - The work to be performed under this contract includes removal and replacement of
existing concrete including concrete pavement, crosspan, sidewalk, curb and gutter, curb ramps, asphalt
patching, various depths and types of milling of existing asphalt pavement, and various thicknesses of asphalt
paving within the streets listed in the Appendices or as directed by the Project Manager. The Contractor shall
supply all labor, equipment, and materials necessary to complete the work in accordance with these
specifications. The contract shall be awarded based on bids received for the base bid schedule A and the
contract documents. Night work shall be required and entail asphalt patching, asphalt milling, and
asphalt overlay on 4th Street, between UPRR and Elbert Street, and 2nd Street between UPRR and
Perry Street, as indicated in the maps. Work shall begin June 20, 2023 and be completed before July
21, 2023. Contractor will be required to coordinate construction activities with adjacent businesses, trash
removal companies, school district, HOA, Metro Districts, and other Town maintenance projects if applicable.
The contractor shall commence work no later than three (3) calendar days from, and including, the date of
the Notice to Proceed, and be construction complete (punchlist items, cleanup, and demobilize) within one
hundred and sixty (160) working days from the date on the Notice to Proceed. If “Construction Completion”
is not issued within the allotted contract time for the original scope of work, “Liquidated Damages” shall be
assessed. When contract work is complete, the contractor shall commence work on punchlist items, cleanup,
and demobilizing regardless of contract time remaining. Work shall take place between April 3, 2023 and
November 3, 2023. A schedule of sequencing of all work shall be submitted at or before the project preconstruction
meeting, and approved by the Town prior to issuance of Notice to Proceed.